Status Report On The Operations Of The Site At Dieu Merci
At the beginning of December, the third ball mill at the Dieu Merci plant was commissioned. The tonnage processed daily approached 300 tons on some days. The effective transition to the nominal production of 300 tons/day is expected to be achieved during the month of January 2021. The 3 ball mills are now operational on the site at Dieu Merci